Coppenrath & Wiese, Atter

Completion of a deep frozen high-bay warehouse

builder-owner: Conditorei Coppenrath & Wiese GmbH & Co. KG

building area: 3210 m²

floor area: 3210 m²

Volume: 101.210 m³

Construction start: June 2020
Construction finish: June 2021

Service phases 1-8 (according to HOAI)

  1. Preliminary assessment
  2. Preliminary design planning
  3. Design planning
  4. Planning for permit applications
  5. Construction planning
  6. Preparation of tenders
  7. Assistance in tenders
  8. Site supervision